Road paving scheduled in Franklin Township

07/10/2013 09:17AM ● By Acl

By John Chambless

Staff Writer

 

Franklin Township has announced its schedule of road paving and repairs for July and August.

The work, to be performed by Innovative Construction, is subject to change, depending on weather conditions.

Stone swales will be added to Flint Hill Road on July 17 and 18, along with some stone work being done on Walker Road on the same dates.

Base repairs are to be made to Glennann Road (July 23 to 25), Hidden Springs Road (July 29), and Flint Hill Road (July 30 and 31).

Base repair and milling work is scheduled for Quail Road (Aug. 1 to 6), and for Walker Road (Aug. 6).

Paving work is scheduled for Walker Road on Aug. 7, Quail Road on Aug. 8, Flinthill Road on Aug. 12, and Glennann Road on Aug. 13.

For updated information, call the township at 610-255-5212 or visit www.franklintownship.us.